During the president’s trip to khoozestan, three west Karoon Development schemes were formally opened.
Significant numbers:
According to the targeted development capacity daily production is:
The first phase of Yadavaran: 85 thousand barrels
The first phase of north azadegan: 75 thousand barrels
North yaran: 30 thousand barrels
Current daily production capacity created:
Yadavaran: 135 thousand barrel
North azadegan: 85 thousand barrel
North yaran: 35 thousand barrel
Current daily production:
Yadavaran: 115 thousand barrel
North azadegan: 75 thousand barrel
North yaran: 30 thousand barrel
Publish Date : 2016/11/19