  • Speaking to Shana, Alireza Ebadi said the first gas recovered from the phase was processed and injected to the national gas trunkline after 42 hours since its recovery which is a new recover in Iran.

    He said production of natural gas from the phase will reach its maximum by the weekend from currently 480 million cubic feet/day.

    The offshore platform of phase 21 can recover 27 million cubic meters of natural gas per day which after processing can supply 25 million cubic meters of sweet gas.

    Up to January 21, 2017, the third and fourth sweetening stations of the phase will be ready to yield gas operation and exploitation of platform 20 are completed.

    Alike the platform for phase 21, the platform of phase 20 has the extraction capacity of 28 million cubic meters/day gas (equal to one billion cubic feet), which was fixed on its jacket on November 12. For the time being, the platform is getting operational.

    Phases 20 and 21 of South Pars, have the capacity for extraction of 56 million cubic meters of sour gas a day, and once they are operational, after completion of the refining and sweetening operations, 50 million cubic meters of sweet gas will be injected to the nationwide network.

    Among other goals behind implementation of the mega project are production and export of 77,000 barrels/day of gas condensates, one million tons/year of liquid gas, 400 tons/year of sulfur and one million tons/year of ethane as feed stock for the petrochemical units.

    For now, the capacity for extraction from South Pars gas field has reached more than 515 million cubic meters/day.

    The goal behind development of phases 20 and 21 of South Pars is daily shipment of 50 million cubic meters of sweet gas to nationwide network to address domestic need, daily production of 75,000 barrels of gas condensates, 400 tons of sulfur, and annual production of 1.05 million tons of liquid gas as well as one million tons of ethane gas to secure feedstock for the petrochemical industries’.

    South Pars gas field is one of the biggest independent gas sources worldwide, lying on Iran-Qatar joint maritime border in Persian Gulf. The field stretches on 9,700 square kilometers of land and Iran’s share is 3,700 km out of the total. On this basis, the field has 14 trillion cubic meters of gas along with 18 billion barrels of gas condensates, which constitute for more than eight percent of the world total gas reserves and close to half of Iran’s gas reserves.

    Qatar started gas extraction from South Pars in 1989 and Iran started the operation as of 2011 actually. As the current government took office in 2013, the policies for development of phases of South Pars and narrowing down the gap with Qatar were prioritized by the Ministry of Petroleum. Since 2014, phases 12, 15 and 16 and parts of phases 17 and 18 of South Pars were put into operation.

    This year, there are plans to put into operation the remaining phases, namely phases 17, 18 and 19, which is equal to two standard phases, and phases 20 and 21 so as to dramatically narrow down the gap of gas exploitation with Qatar. In not far future, the production of the two countries will equal.

Publish Date : 2016/12/20